RFI, MIR, WIR and NCR in Piping: What Each QC Document Does

What an NCR in piping is and how RFI, MIR and WIR fit with it: what each QC document should contain and the mistakes that get a request rejected.

By Syed Hasan24 Nov 20268 min read

RFI, MIR, WIR and NCR in Piping: What Each QC Document Does

On a piping construction site, the quality of the work is judged twice: once by the inspector looking at it, and again, months later, by anyone reading the paperwork that says it was looked at. If a spool was fitted, welded, tested and accepted, there should be a document trail that proves each step. When that trail is missing or sloppy, a sound weld can still be rejected, and a bad one can slip through.

This post explains the four documents a piping QC inspector deals with every day: the RFI, MIR, WIR and NCR. You will see what each one is for, what a good one contains, how they fit together from material receiving to final acceptance, when an NCR in piping is raised and closed, and the mistakes that get a request sent back.

A word on names before we start

These are project documents, not industry-wide standard forms. Their names, numbering and exact scope differ between contractors, clients and projects. Some projects use RFI and WIR for different things; others use only one of them for every inspection request. The project's quality plan and its inspection and test plan (ITP) define what applies on your job. Read them first, and treat the descriptions below as the common pattern, not a template to impose.

None of these documents is part of a certification syllabus. They are how a project organises inspection, and knowing them well is simply part of working in QA/QC.

MIR: Material Inspection Request

The MIR covers incoming material. Pipes, flanges, fittings, valves, gaskets and bolts are inspected and approved before they can be used. The aim is simple: nothing goes into the system unless it is the right material, the right size and traceable to its certificate.

Typical checks on an MIR include:

  • Material specification and grade against the purchase order and piping specification (the relevant ASTM or ASME material).
  • Size, schedule or wall thickness, pressure rating and quantity.
  • Heat number on the item matched to the mill test certificate, commonly an EN 10204 type 3.1 certificate.
  • Manufacturer or approved vendor.
  • Visual and dimensional condition, and positive material identification (PMI) where the project requires it.
  • Packing list, delivery documents, markings and identification.

The heat number check is the one that matters most later. Once a pipe is cut and welded, the only link between a piece of steel in the field and its test results is the marking and the paperwork.

QC inspector checking the heat number stencilled on a stack of steel pipes against a mill test certificate in a laydown yard
On an MIR, the heat number links the steel to its certificate.

RFI: Request for Inspection

An RFI asks the inspector, and often the client's inspector, to come and inspect and approve a piece of completed work before the next step covers it up. Spool fit-up and erection are typical examples.

A good RFI tells the inspector exactly what, where and when, so nobody has to guess:

  • Line number, area or unit.
  • The activity to be inspected.
  • Isometric drawing and P&ID reference.
  • Spool and joint numbers.
  • Date and time requested.
  • The ITP reference and the inspection point (hold, witness or review).
  • Remarks and the approval status once inspected.

WIR: Work Inspection Request

On projects that use both, the WIR covers inspection of a specific construction activity: fit-up, welding, support installation, hydrotest or flushing. Where the project uses only one request form, this is the same job the RFI does.

The checks depend on the activity, but for welded piping they usually include:

  • Compliance with the isometric or drawing.
  • Alignment, root gap and orientation at fit-up.
  • The WPS and its supporting PQR, and the welder's qualification for that procedure.
  • Visual inspection of the completed weld.
  • NDT (radiography, ultrasonic, dye penetrant or magnetic particle testing) and PWHT as the specification requires.
  • The ITP checklist items for that activity.

For what to look for on radiographs, see reading weld radiographs and defects.

NCR in piping: the Non-Conformance Report

An NCR in piping is raised when work or material does not comply with the approved drawings, the specifications, the governing code (for process piping, often ASME B31.3) or the project's quality requirements. It is not a punishment; it is the formal way of recording a problem so that it is fixed and the fix is checked.

A useful NCR contains:

  • A clear description of the non-conformance, with the requirement it breaks.
  • Evidence: photos, NDT reports or measurements.
  • The corrective action to fix this case, and the preventive action to stop it happening again.
  • The person responsible for the action.
  • Verification of the action and formal closure.

A typical example: a weld defect is found in radiography. An NCR is raised, the root cause is identified and the weld is repaired to an approved repair procedure, the repair is re-inspected, and the NCR is closed once the result is accepted. Repair welding and its inspection are covered in more depth in welding repair and inspection.

Flow diagram of the NCR loop: inspection finds a defect, NCR raised, corrective action, re-inspection, NCR closed
The NCR loop: find, record, fix, re-inspect, close.

Hold, witness and review points

Every request ties back to a line in the ITP, and that line says how much involvement the inspector has. The terms vary a little by project, but the usual meaning is:

  • Hold point. Work stops until the inspection is done and accepted. Nothing proceeds past it without a signature.
  • Witness point. The inspector is notified and may attend. If they do not come within the notice the project allows, work can carry on.
  • Review point. The inspector checks the records afterwards rather than watching the work.

Knowing which kind of point an activity is saves arguments on site, because it decides whether a missing signature stops the job or simply needs following up.

How the four documents fit together

On most piping jobs the flow of piping QC documents runs like this:

  1. Material arrives and is checked on an MIR.
  2. Approved material is released for fabrication and erection.
  3. Each inspection point (fit-up, welding, supports, testing) is requested by RFI or WIR.
  4. Inspection and NDT are carried out and the request is approved or rejected.
  5. Approved work moves to the next stage; the line eventually goes to pressure test and handover.

When something fails, the loop is: inspection finds the problem, an NCR is raised, corrective action is taken, the work is re-inspected, and the NCR is closed. Only then does that item move on.

Side by side, the RFI, MIR, WIR, NCR set looks like this:

DocumentAnswers the questionRaised by (usually)
MIRIs this material right and traceable?Contractor, on receipt
RFIIs this completed work ready to accept?Contractor, before covering up
WIRWas this activity done to the procedure?Contractor, at each ITP point
NCRWhat is wrong, and how was it fixed?Inspector or QC, when a requirement is not met

Why the paperwork is the quality system

It is tempting to see these forms as a burden next to the "real" work. In practice they are what make the work defensible. They give traceability, so any weld or fitting can be traced to its material and its inspection. They prevent rework, because problems are caught at the step where fixing them is cheapest. And they keep the project audit-ready, so a client or third party can confirm the system was built to specification without re-inspecting everything.

Mistakes that get a request rejected

  • Vague location: "line 12" with no spool or joint number.
  • Wrong or missing drawing revision.
  • Requesting inspection before the work is actually ready, which wastes the inspector's visit.
  • Missing attachments: no MTC on an MIR, no NDT report behind a weld acceptance.
  • An NCR that describes the symptom but not the requirement it breaks, or closes with "repaired" and no evidence.
  • Late requests that miss the ITP notice period the project has set.

Frequently asked questions

What is an NCR in piping?

It is a Non-Conformance Report: the formal record raised when piping work or material does not meet the approved drawings, the specification, the governing code (often ASME B31.3 for process piping) or the project's quality requirements. It records the problem, the evidence, the corrective and preventive action, who is responsible, and the verification before it is closed.

What is the difference between RFI and WIR?

On projects that use both, an RFI asks the inspector to inspect and approve completed work before the next step covers it up, while a WIR covers inspection of a specific construction activity such as fit-up, welding, supports or hydrotest. Many projects use only one form for every request, so the project's quality plan and ITP decide which applies.

Who raises an NCR on a construction project?

Usually the inspector or the QC team raises an NCR when a requirement is not met, for example a weld defect found in radiography or material that cannot be traced to its certificate. The contractor then carries out the corrective action, and the NCR stays open until the fix is re-inspected and accepted.

When can an NCR be closed?

Only after the corrective action has been carried out, the work has been re-inspected, and the result is accepted with evidence such as a new NDT report or measurements. An NCR closed with the single word "repaired" and nothing behind it is one of the common mistakes, because nobody reading it later can confirm the fix.

Where to go from here

Strong QC paperwork habits are a good foundation for a move into inspection and integrity roles. If you work on welded piping, the CSWIP 3.1 welding inspector preparation builds the inspection knowledge behind the WIR checks. For in-service piping, the API 570 piping inspector certification preparation is the natural next step. The welding repair and inspection course covers repair work behind many NCRs, and carbon steel piping components is a good refresher on the items an MIR checks.

Exam preparation

Preparing for API 570?

Practise with exam-style questions, timed mocks and study notes. 1,841 questions in the bank.

Also relevant: CSWIP 3.1 Welding Inspector