A tank has four main parts. The foundation carries the weight, the bottom holds the liquid and sits on the foundation, the shell is built from stacked rings called courses, and the roof closes the top. Nozzles, manways and fittings pass through them.

  • Foundation: a ring wall or a compacted pad that spreads the load of the tank and its contents.
  • Bottom: steel plates on the foundation; the outer ring, the annular plates, is thicker because it carries more stress.
  • Shell: rings (courses) of plate welded one above the other, thicker at the bottom where the liquid pressure is greatest.
  • Roof and fittings: the roof closes the top; nozzles, manways, ladders and gauging devices pass through the shell and roof.

Every tank, whatever its roof, is built from the same four parts, and each part fails in its own way.

The foundation carries everything. It may be a concrete ring wall with a compacted fill inside, or a prepared pad of crushed stone or sand. Its job is to spread the weight so the tank settles evenly, to drain water away, and to keep the bottom plates dry. If it fails, the damage appears above it.

The bottom is a set of steel plates lap-welded together and resting on the foundation. Around the edge, where the shell sits, the plates are thicker. These annular plates take extra stress and are a common place for trouble. The underside of the bottom is hard to inspect, which makes it one of the main concerns for inspectors.

The shell is built in rings called courses, each welded to the next. The lowest course is the thickest because the liquid pressure is highest there. The top of the shell often carries a stiffening angle or a wind girder that helps it keep its round shape.

The roof closes the top, and its type decides how the tank breathes. Through the shell and roof pass nozzles, manways, drains, ladders, gauging devices and earthing connections. Each opening is a potential leak point and a stress concentration, so they get special attention.

Good practice

  • Learn the name and position of every part before you describe a defect.
  • Record the location of a finding by course number and position around the tank.

Avoid

  • Do not treat the foundation as someone else's problem.
  • Do not forget the connection points: nozzles and manways concentrate stress.

In the field

Sketch the tank as you walk it, with north marked and courses numbered from the bottom. A findings list with no location is of little use to the next inspector.

Course:
one horizontal ring of shell plates.
Annular plate:
the thicker bottom plate ring around the edge of the floor.
Ring wall:
a concrete wall under the shell that carries the shell load.

Based on: API 650, API 653, API 575. A summary for learning. The standard and your site procedures govern.

Preparing for an exam? Take it with you.

The EIM app has study notes, practice questions with explanations, timed mock tests and your progress, on your phone. Free to download. Android first, iPhone to follow.

Get it on Google Play